Material from a base warehouse earmarked for a specific project, so nobody takes it before the crew starts installing. When the material goes to site, you issue the reservation; when it turns out not to be needed, you release it.

IN THE APP
Modules › Materials and equipment › Material reservations
AVAILABLE
Stock minus reservations
STATUSES
Reserved, issued, released
CONNECTIONS
5 modules

01What it is

A reservation earmarks material from one location for a project. Physical stock does not change, but the available quantity drops at once.

When the project’s site has a base, you reserve only in its warehouse, and never more than is available. The warehouse is suggested automatically.

Issuing takes the material out of stock as used on the project. Releasing returns it to the available pool. An issued or released reservation stays on the list as history.

STOCK UNCHANGED
A reservation lowers the available quantity, not physical stock.
PROJECT WAREHOUSE
You reserve in the warehouse of the site’s base.
NOT COVERED
Available below zero is visible at once.

02What it is for

Material waits for the crew

Reserved material is not available for another project.

Issue to site

One click takes the material out of stock and assigns it to the project.

Shortages before installation

The Not covered tile counts reservations without cover in stock.

Honest stock

Stock levels show what is available after reservations.

03Main options

The screen has a list of reservations with tiles, the new reservation window and the issue and release actions.

Material, project, location and available

Tiles: all reservations, reserved, not covered and issued.

  • Columns: product with quantity, project, location, physical stock, reserved, available, status
  • Filters: warehouse, status and project; search by material and project
  • Row preview with the note and a link to the project record
Reservations list

04Tasks step by step

  1. STEP 1Open Modules › Materials and equipment › Material reservations and choose New reservation.
  2. STEP 2Choose the product and the project. The location is suggested from the base of the site.
  3. STEP 3Enter the quantity and save.

05Actions

The most common tasks for reservations.

New reservation

Material earmarked for a project.

Issue

Material leaves stock for the project.

Release

Material returns to the available pool.

Project filter

All reservations of one project.

06What it connects to

Choose a module to see how reservations affect stock and projects.

MATERIALS AND EQUIPMENT

Stock levels

Reservations lower the available quantity in stock levels.