Requirements

A list of the materials missing for a project or for the warehouse, before the order goes to a supplier. First you check whether the material is already sitting as surplus at another base, then you collect offers from several suppliers and choose one.

IN THE APP
Modules › Suppliers and subcontractors › Requirements
STATUS
Needed
OFFERS
Cheapest and fastest
CONNECTIONS
5 modules

01What it is

A requirement is a material order with the Needed status: you know what is missing, but you have not placed the order yet. Requirements and Orders are the same register; the Requirements screen opens it with the Needed filter already set.

A requirement belongs to a project or goes to stock, with no project. The supplier can be left as to be decided. You add items from the catalogue or enter them manually, with a catalogue number and a quantity.

While the status is Needed, people with finance access collect offers from several suppliers on the Offers tab. The application marks the cheapest and the fastest, and the chosen offer sets the supplier and the delivery date.

ONE REGISTER
A requirement changes status and becomes an order.
PROJECT OR STOCK
Material for a project or for stock.
OFFERS TO COMPARE
The cheapest and the fastest are marked automatically.

02What it is for

What is holding a project up

The project filter shows the materials it is missing.

Surplus first

A shortcut to surplus: is the material already at another base?

A better price

Offers from several suppliers with an amount, a delivery date and a validity date.

Ready to order

Change the status to Ordered without retyping the items.

03Main options

Requirements is the material order register narrowed to the Needed status, with a form, items and offers.

Number, project, site, supplier and deadline

Tiles: all orders, needed, ordered / in transit, value in progress (with finance access).

  • Filters: project, status (Needed by default), category and group
  • Search by number, project and supplier, CSV export
  • The Surplus across sites shortcut in the screen menu
Requirement list

04Tasks step by step

  1. STEP 1Open Modules › Suppliers and subcontractors › Requirements and choose New requirement.
  2. STEP 2Choose a project or “To stock, no project” and save.
  3. STEP 3On the Items tab add materials from the catalogue or enter them manually.

05Actions

The most common tasks for requirements.

New requirement

Material for a project or for stock.

Surplus across sites

Is it already sitting somewhere?

Add offer

Amount, delivery date and validity.

Mark as: Ordered

The requirement becomes an order.

06What it connects to

Choose a module to see what happens to a requirement next.

SUPPLIERS AND SUBCONTRACTORS

Orders

Once its status changes, a requirement is an order.

Go to the topicOrders