MIVARE LABS SITES CONSTRUCTION MANAGEMENT SOFTWARE
Absences. Mivare Sites Help Centre
AREA 02 · PEOPLE AND PLANNING · TOPIC 05

Absences

A holiday entered once covers a whole week of planning. The absent person leaves the site plan, the dashboard and the phone, and a task assigned to them in that period lights up in the schedule as a conflict before anyone drives to an empty site.

IN THE APP
Modules › People and planning › Absences
KEPT FOR
Every person in the team
AFFECTS
Site plan and schedule
CONNECTIONS
5 modules

01What it is

An absence is a period in which a team member does not work on sites: a holiday, sick leave, training or another absence. You enter the person, the type, the first and the last day, and the application counts the days and makes sure two absences of the same person do not overlap.

The entry changes the plan at once. A person absent on a given day is not planned on any site, so they do not appear among the planned on the dashboard, on the phone or in the expected days of the timesheet. A task assigned to them in that period shows in the schedule as a conflict.

Deleting an absence returns the person to the plan for those days. When a holiday gets shorter, simply correct the end date in the same entry.

ONE REGISTER
Holidays, sick leave and training for the whole team.
A PLAN WITHOUT MISTAKES
An absent person leaves the site plan.
CONFLICTS AT ONCE
A task during an absence shows in the schedule.

02What it is for

Who is unavailable today

The Absent today tile counts people with an ongoing absence.

Holidays in advance

The Planned in the next 30 days tile shows what is coming this month.

Conflicts in the schedule

A task of an absent person does not go unnoticed.

Accurate timesheets

Days of absence are not expected working days.

03Main options

The screen has tiles, filters and one table of absences with a dialog for entries.

Who, when and why

One table for the whole team, with filters by person, type and period.

  • Person, type, first and last day
  • Number of days and notes
  • An Ongoing marker on today’s absences
  • Period: ongoing, planned, finished
Absence list

04Tasks step by step

  1. STEP 1Open Modules › People and planning › Absences.
  2. STEP 2In the Actions menu choose New absence.
  3. STEP 3Pick the person, the type Holiday, the first and the last day, then save.

05Actions

The most common tasks on the absences screen.

New absence

Holiday, sick leave or training.

Edit

Change the person, type, dates or notes.

Filters

Person, type and period of absence.

CSV export

The table as shaped by the current filters.

06What it connects to

Choose a module to see where an absence changes the plan.

PEOPLE AND PLANNING

Schedule

A task assigned to an absent person is a schedule conflict.

Go to the topicSchedule